Repairs

6.0 – Material Selection

6.1 – Phase 1 – Windows and Doors- Identifying the best materials for the doors and windows that will ensure quality and efficiency.

6.1.1 – Equipment- With aid of the Construction Authority, we will research on the best equipment for the renovation process.

6.1.1.1 – Research Dumpster Rental Prices- research on the right size dumpster for the renovation project which will determine the prices.

6.1.1.2- Select Dumpster Rental Company- Identify the different Dumpster Rental companies to decide on the one with the best offer.

6.1.1.3 – Select Rental Time Frame- Using grant chart to determine the rental time frame in which the renovation process will be ongoing.

6.1.1.4 – Sign Rental Contract- After agreeing to the best terms we can sign the rental contract.

6.1.1.5 – Submit Payment- With help of our bank, we will make payments to the contracted company.

 

6.1.2 – Research Doors

6.1.2.1 – Determine LEED Approved Materials – Using the LEED website, determine all the approved materials for the doors.

6.1.2.2 – Select Material (worth most leed points)- Among the different LEED approved materials, select the most appropriate materials.

6.1.2.3 – Measure and Record Door Sizes- Using the acceptable measuring standards, measure and record the door sizes accordingly.

6.1.2.4 – Determine Quantity of Each Door Size- With the help of quantity surveyor, determine the quantity of each door size.

 

6.1.3 – Research Windows

6.1.3.1 – Determine LEED Approved Materials- Using the LEED website, determine the approved window materials.

6.1.3.2 – Select Material- With the help of the list of the LEED approved materials, select the most appropriate materials.

6.1.3.3 – Measure and Record Window Sizes- Make the necessary recordings and measurement of the different windows.

6.1.2.4– Determine Quantity of Each Window Size- With the help of a quantity surveyor, determine the quantity of each window size.

 

6.1.4 – Shop Doors& Hardware

6.1.4.1 – Compare Supplier Prices- Identifying the different suppliers and their prices to get the most cost effective supplier.

6.1.4.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier.

6.1.4.3 – Order Doors –After identifying the best supplier, make an order accordingly.

6.1.4.4 – Research Door Hardware- Using the LEED website, research on recommended door hardware.

6.1.4.5 – Select Door Hardware– Using the information from LEED, select on the door hardware.

6.1.4.6 – Pay for Doors & Hardware- After selecting door hardware make the necessary payments.

6.1.4.7 – Schedule Delivery- Ensure effective delivery of the ordered hardware.

 

6.1.5 – Shop Windows- Identifying the different suppliers and their prices to get the most cost effective supplier.

 

6.1.5.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.1.5.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.1.5.3 – Order Windows -After identifying the best supplier, make an order accordingly.

6.1.5.4 – Pay for Doors- After selecting door hardware make the necessary payments.

 

6.1.5.5 – Schedule Delivery- Organize for the delivery of windows.

 

6.2 – Phase II

6.2.1 – Equipment- With aid of the Construction Authority, we will research on the best equipment for the renovation process

6.2.1.1 – Research Dumpster Rental Prices- research on the right size dumpster for the renovation project which will determine the prices

6.2.1.2- Select Dumpster Rental Company- Identify the different Dumpster Rental companies to decide on the one with the best offer.

 

6.2.1.3 – Select Rental Time Frame- Using grant chart to determine the rental time frame in which the renovation process will be ongoing

6.2.1.4 – Sign Rental Contract- After agreeing to the best terms we can sign the rental contract with the help of a lawyer.

6.2.1.5 – Submit Payment- After the agreement, payments should be made with the help of our bank.

 

6.2.2 – Research Electrical- Identify the electrical works required in the renovation process.

6.2.2.1 – Measure and Record Length Needed- With the help of an electrical engineer, measure and record the length needed accordingly.

6.2.2.2 – Adjust Estimate for Error- with the help of the electrical department, adjust estimates for error.

 

6.2.3 – Research HVAC Ductwork- Using LEED website research on HV AC Ductwork.

6.2.3.1 – Determine LEED Approved Materials- Using LEED website determines the LEED approved electrical materials.

6.2.3.2 – Select Ductwork- Using the list of the approved materials; select the effective and efficient Ductwork.

6.2.3.3 – Determine Length of Ductwork Needed- Using the recommended measurements, determine the length of the Ductwork needed.

 

6.2.4 – Research Lighting- With the help of the new Science Building, research on the expected lighting.

6.2.4.1 – Determine LEED Approved Materials- Using the LEED website, determine the LEED approved materials.

6.2.4.2 – Select Lighting- With the help of the of the LEED list select most appropriate lighting.

6.2.4.3 – Determine Number of Fixtures- with the help of an engineer determine the number of fixtures.

6.2.4.4 – Determine Fixtures to Change- identify the necessary fixtures that need to be changed.

 

6.2.5 – Shop Electrical Wiring

6.2.5.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.2.5.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.2.5.3 – Order Wiring- After identifying the best supplier, make an order accordingly.

6.2.5.4 – Pay for Wiring– After selecting electrical wiring make the necessary payments

6.2.5.5 – Schedule Delivery- Organize for the delivery of wiring

6.2.5.6 – Accept Delivery-Accept delivery by signing necessary documents and after confirming the right order has been delivered.

 

6.2.6 – Shop HVAC Ductwork

6.2.6.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.2.6.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.2.6.3 – Order Ductwork- After identifying the best supplier, make an order accordingly.

6.2.6.4 – Pay for Ductwork- After selecting Ductwork make the necessary payments

6.2.6.5 – Schedule Delivery- Organize for the delivery of Ductwork

6.2.6.6 – Accept Delivery- Accept delivery by signing necessary documents and after confirming the right order has been delivered

6.2.7 – Shop Lighting

6.2.7.1 – Compare Supplier Prices Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.2.7.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.2.7.3 – Order Lighting- After identifying the best supplier, make an order accordingly

6.2.7.4 – Pay for Lighting- After selecting Ductwork make the necessary payments with the help of our bank.

6.2.7.5 – Schedule Delivery- Organize for the delivery of lighting.

 

6.2.7.6 – Accept Delivery- Accept delivery by signing necessary documents and after confirming the right order has been delivered

6.3 – Phase III

6.3.1 – Research Paint

6.3.1.1 – Determine LEED Approved Paints – using the LEED website research on the approved paints.  

6.3.1.2 – Determine Amount of Paint Needed– with the help of a quantity surveyor, determine the amount of paint required.

6.3.2 – Research Flooring

6.3.2.1 – Determine LEED Approved Material- using LEED website determine the approved flooring materials.

6.3.2.2 – Determine SHPO Approved Material- identify the SHPO approved material.

6.3.2.3 – Determine Amount of Flooring Needed- with the help of a quantity surveyor, determine the amount of flooring materials required.

6.3.3 – Research Desks

6.3.3.1 – Research LEED Certified Materials- Using the LEED website, research on the Leed certified materials for making desks.

6.3.3.2 – Determine and Record the Types of Desks Needed- make formal arrangements on the number and types of desks needed.

6.3.3.3 – Determine and Record Quantity of Each Desk Type- with the help of a quantity surveyor determine the quantity of materials for each desk type.

6.3.4 – Research Seating

6.3.4.1 – Research LEED Certified Materials -Using the LEED website, research on the Leed certified materials for making seating.

6.3.4.2 – Determine and Record the Types of Seating Needed- make formal arrangements on the number and types of seating needed.

6.3.4.3 – Determine and Record Quantity of Each Seating Type- with the help of a quantity surveyor determine the quantity of materials for each desk type.

 

6.3.5 – Research HVAC Units

6.3.5.1 – Research LEED Approved Units- Using the LEED website, research on the Leed certified materials for making seating.

 

6.3.5.2 – Determine the Building Cooling Load- with the help of construction engineers, determine the building cooling load.

6.3.5.3 – Determine the Building Heating Load- with the help of construction engineers, determine the building heating load.

 

6.3.5.4 – Determine Number of Units Needed- using the acceptable measuring standards, determine the number of units needed.

 

6.3.6 – Shop Paint

6.3.6.1 – Compare Supplier Prices- Prices Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.6.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.6.3 – Order Paint- After identifying the best supplier, make an order accordingly

 

6.3.6.4 – Pay for Paint- After selecting and ordering the right paint, make the necessary payments with the help of our bank.

 

6.3.6.5 – Pick Up Paint- Organize the collection of the paint for effective delivery.

 

6.3.7 – Shop Flooring

6.3.7.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.7.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.7.3 – Order Flooring- After identifying the best supplier, make an order accordingly

6.3.7.4 – Pay for Flooring After selecting and ordering the right flooring, make the necessary payments with the help of our bank

6.3.7.5 – Schedule Delivery -Organize for the delivery of flooring.

6.3.7.6 – Accept Delivery- Accept delivery by signing necessary documents and after confirming the right order has been delivered

 

6.3.8 – Shop Desks

6.3.8.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.8.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.8.3 –Order Desks- After identifying the best supplier, make an order accordingly

6.3.8.4 – Pay for Desks- After selecting and ordering the right desks, make the necessary payments with the help of our bank

 

6.3.8.5 – Schedule Delivery- Organize for the delivery of the ordered desks.

6.3.8.6 – Accept Delivery- Accept delivery by signing necessary documents and after confirming the right order has been delivered.

 

6.3.9 – Shop Seating

6.3.9.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.9.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.9.3 – Order Seating- After identifying the best supplier, make an order accordingly

6.3.9.4 – Pay for Seating- After selecting and ordering the right desks, make the necessary payments with the help of our bank

6.3.9.5 – Schedule Delivery – Organize for the delivery of the ordered seating

6.3.9.6 – Accept Delivery-. Accept delivery by signing necessary documents and after confirming the right order has been delivered.

 

 

6.3.10 – Shop HVAC Units

6.3.10.1 – Compare Supplier Prices- Using the information gathered on prices offered by the different suppliers, select the most effective supplier

6.3.10.2 – Select Supplier- Using the information gathered on prices offered by the different suppliers, select the most effectiv After identifying the best supplier, make an order accordingly e supplier

6.3.10.3 – Oder HVAC Units- After identifying the best supplier, make an order accordingly

 

6.3.10.4 – Pay for HVAC Units – After selecting and ordering the HV AC units, make the necessary payments with the help of our bank

6.3.10.5 – Schedule Delivery- Organize for the delivery of the ordered HV AC units.

 

6.3.10.6 – Accept Delivery- Accept delivery by signing necessary documents and after confirming the right order has been delivered.

 

7.0 – Asbestos Removal

7.1 – Phase I

7.1.1 – Pre Abatement- With the help of the construction Authority, prepare for the actual abetement process

7.1.1.1 – Take Preliminary Air Samples- with the help of the construction engineers takes preliminary air samples.

7.1.1.2 – Seal Workspace– Ensure that the work place is sealed to avoid interference.

7.1.1.3 – Install Negative Air Machines- Identify the best machines to reduce air pollution.

7.1.1.5 – Remove Power to HVAC Unit– with the help of electrical engineers, remove the HV AC units for the workers safety.

7.1.1.6 – Install Temporary Electrical Power- with help of electrician install temporary electricity to provide power during   the removal.

 

7.1.1.7 – Erect Decontamination Enclosure Systems- Identify decontamination enclosure systems to reduce the level of contamination during the renovation process.

7.1.1.8 – Remove Moveable Objects from Space- removal of movable objects from the space is essential for the safety of the workers.

7.1.1.9 – Seal Non Moveable Objects- with the help of the laborers, seal the non-movable objects from the space.

7.1.1.10- Plasticize Surfaces- With the help of construction engineer, plasticize the space  

7.1.1.11 – Start Negative Air Machines- with the help of the environment department, start negative air machines to prevent air pollution.

 

7.1.2 – Abatement

7.1.2.1 – Remove Windows-with the help of the casuals, remove the windows

7.1.2.2 – Remove Window Caulk- Lessen the levels of window caulk to make the abatement work easier.

7.1.2.3 – Dispose of Windows and Window Caulk. –Disposal of thes e windows and window caulk should be in accordance with the environment authority.

 

7.1.3 – Post Abatement

7.1.3.1 – Remove Equipment- after the abatement process, all the equipment used in the exercise should be removed.

7.1.2.2 – Wet Wipe All Surfaces- Casuals should wet wipe all the surfaces to reduce dust levels.

7.1.3.3 – Wait Period- after the abatement process there should be wait time to allow the dust to settle.

7.1.3.4 – Remove Plastic. The construction engineer should help remove the plasticized surface.

7.1.3.5 – Reclean All Surfaces- Recleaning all the dirty surfaces is necessary.

7.1.3.6 – Wait Period- After the cleaning a short wait period.

7.1.3.7 – Remove Plastic. – Plasticized surface must be cleaned up.

7.1.3.8– Reclean All Surfaces- cleanliness must be maintained at all times.

7.1.3.9 – Wait Period- Post abatement must ensure there is enough wait period.

7.1.3.10 – Visual Inspection- with the help of engineers, carry out continuous visual inspection

7.1.3.11 – Air Quality Inspection– the quality of air should be ascertained by the environment department.

7.2 – Phase II

7.2.1 – Pre Abatement

7.2.1.1 – Take Preliminary Air Samples- with the help of the construction engineers takes preliminary air samples.

7.2.1.2 – Seal Workspace- Ensure that the work place is sealed to avoid interference

7.2.1.3 – Install Negative Air Machines- Identify the best machines to reduce air pollution.

7.2.1.5 – Remove Power to HVAC Unit- with the help of electrical engineers, remove the HV AC units for the workers safety.

7.2.1.6 – Install Temporary Electrical Power- with help of electrician install temporary electricity to provide power during   the removal.

7.2.1.7 – Erect Decontamination Enclosure Systems- Identify decontamination enclosure systems to reduce the level of contamination during the renovation process

7.2.1.8 – Remove Moveable Objects from Space- removal of movable objects from the space is essential for the safety of the workers.

 

7.2.1.9 – Seal Non Moveable Objects– with the help of the laborers, seal the non-movable objects from the space.

7.2.1.10- Plasticize Surfaces – With the help of construction engineer, plasticize the space 

7.2.1.11 – Start Negative Air Machines– with the help of the environment department, start negative air machines to prevent air pollution.

7.2.2 – Abatement

7.2.2.1 – Remove Windows -with the help of the casuals, remove the windows

7.2.2.2 – Remove Window Caulk– Lessen the levels of window caulk to make the abatement work easier.

7.2.2.3 – Dispose of Windows and Window Caulk- Disposal of thes e windows and window caulk should be in accordance with the environment authority

7.2.3 – Post Abatement

7.2.3.1 – Remove Equipment– after the abatement process, all the equipment used in the exercise should be removed.

7.2.2.2 – Wet Wipe All Surfaces- Casuals should wet wipe all the surfaces to reduce dust levels

7.2.3.3 – Wait Period- After the cleaning a short wait period.

7.2.3.4 – Remove Plastic- Plasticized surface must be cleaned up

7.2.3.5 – Reclean All Surfaces– cleanliness must be maintained at all times.

7.2.3.6 – Wait Period- Post abatement must ensure there is enough wait period.

7.2.3.7 – Remove Plastic- Plasticized surface must be cleaned up

7.2.3.8 – Reclean All Surfaces- Recleaning all the dirty surfaces is necessary.

7.2.3.9 – Wait Period- Post abatement must ensure there is enough wait period.

7.2.3.10 – Visual Inspection- with the help of engineers, carry out continuous visual inspection

7.2.3.11 – Air Quality Inspection- the quality of air should be ascertained by the environment department.

7.3 – Phase III

7.3.1 – Pre Abatement

7.3.1.1 – Take Preliminary Air Samples– with the help of the construction engineers takes preliminary air samples.

7.3.1.2 – Seal Workspace- Ensure that the work place is sealed to avoid interference

7.3.1.3 – Install Negative Air Machines- Identify the best machines to reduce air pollution

7.3.1.5 – Remove Power to HVAC Unit- with the help of electrical engineers, remove the HV AC units for the workers safety.

 

7.3.1.6 – Install Temporary Electrical Power– with help of electrician install temporary electricity to provide power during   the removal.

7.3.1.7 – Erect Decontamination Enclosure Systems- Identify decontamination enclosure systems to reduce the level of contamination during the renovation process

7.3.1.8 – Remove Moveable Objects from Space– removal of movable objects from the space is essential for the safety of the workers.

7.3.1.9 – Seal Non Moveable Objects- with the help of the laborers, seal the non-movable objects from the space.

7.3.1.10- Plasticize Surfaces – With the help of construction engineer, plasticize the space 

7.3.1.11 – Start Negative Air Machines- with the help of the environment department, start negative air machines to prevent air pollution

7.3.2 – Abatement

7.3.2.1 – Remove Flooring- removal of the old flooring is necessary.

7.3.2.2 – Remove Plaster- with the help of casuals remove the old plaster

7.3.2.3 – Dispose of Flooring and Plaster– the removed plaster and flooring must be disposed in accordance with the environment department.

7.3.3 – Post Abatement

7.3.3.1 – Remove Equipment— after the abatement process, all the equipment used in the exercise should be removed.

7.3.2.2 – Wet Wipe All Surfaces- Casuals should wet wipe all the surfaces to reduce dust levels

7.3.3.3 – Wait Period- After the cleaning a short wait period

7.3.3.4 – Remove Plastic- Plasticized surface must be cleaned up

7.3.3.5 – Reclean All Surfaces– Recleaning all the dirty surfaces is necessary

7.3.3.6 – Wait Period– Post abatement must ensure there is enough wait period

7.3.3.7 – Remove Plastic- Plasticized surface must be cleaned up

7.3.3.8 – Reclean All Surfaces- cleanliness must be maintained at all times

7.3.3.9 – Wait Period- Post abatement must ensure there is enough wait period

7.3.3.10 – Visual Inspection- with the help of engineers, carry out continuous visual inspection

7.3.3.11 – Air Quality Inspection – the quality of air should be ascertained by the environment department.

8.0 – Construction

8.1 – Phase I

8.1.1 – Bricked Over Windows- with the help of construction engineers determine the bricked over windows.

8.1.1.1 – Remove Items from Impacted Work Spaces- with the help of the casuals, ensure that all items from the impacted works are removed.

8.1.1.3 – Remove Brick from Covered Windows– Ensure that all windows are uncovered from bricks.

8.1.1.4 – Reframe Restored Windows- with help of construction engineers, ensure that all windows are uncovered from bricks

8.1.1.5 – Install New Windows- renovation process aimed at replacing the old features with new ones.

8.1.1.6 – Paint New Windows and Frames- after installing windows and framing them, it is important to paint them accordingly.

8.1.2 – Standard Windows

8.1.2.1 – Reframe Windows- with help of construction engineers, ensure that all windows are uncovered from bricks

8.1.2.2 – Install New Windows- renovation process aimed at replacing the old features with new ones.

8.1.2.3 – Paint New Windows and Frames– after installing windows and framing them, it is important to paint them accordingly.

8.1.3 – Doors

8.1.3.1 – Remove Items from Impacted Work Spaces- with the help of the casuals, ensure that all items from the impacted works are removed.

 

8.1.3.2 – Remove Old Doors- all the old doors should be removed.

8.1.3.3 – Reframe Doors- the good doors should be reframed.

8.1.3.4 – Install New Doors- the new doors should be installed and replace the old ones.

8.1.3.5 – Install Door Hardware- the purchased hardware should be installed on the newly placed doors.